Compare multifamily siding bids line by line

Use a scope table, clarification register and selection memo to compare apartment and condo siding proposals fairly.

Request a siding review

Prepared by The Hammer Mill · Sources checked September 2026 · Editorial approach

A bid comparison should show whether contractors priced the same work. Put the required scope in one column and each bidder’s response beside it. Mark an unanswered item as not stated. Do not turn silence into an inclusion or assign an invented cost to make the totals look comparable.

This worksheet is an owner-side organizing tool. It does not replace technical specifications or contract review.

Start with a common description

Give each bidder the same dated packet: building list, elevation register, measured drawings if available, condition report, proposed product options, access constraints, and required handover documents. Number every revision. If a site walk reveals a condition that affects pricing, circulate the clarification to everyone invited to bid.

Scope itemRequired responseBid ABid BBid C
Buildings and elevationsIdentifiers and removal limitsNot statedNot statedNot stated
Measurement basisQuantities and treatment of openingsNot statedNot statedNot stated
Existing material removalLayers, trim, disposal, excluded workNot statedNot statedNot stated
Proposed productManufacturer, product, profile, finishNot statedNot statedNot stated
Water-management workBarrier, flashing, connections, exclusionsNot statedNot statedNot stated
Concealed repairsAllowance or unit rates, inclusions, approval processNot statedNot statedNot stated
Design and permitsResponsible party and fee inclusionsNot statedNot statedNot stated
AccessEquipment, staging, parking, restricted areasNot statedNot statedNot stated
Resident coordinationNotice responsibility and access planNot statedNot statedNot stated
Building protectionWindows, landscaping, walkways, cleanupNot statedNot statedNot stated
Testing or special handlingAvailable reports and excluded investigationsNot statedNot statedNot stated
ScheduleMobilization assumptions and building sequenceNot statedNot statedNot stated
WarrantyProduct and workmanship documentsNot statedNot statedNot stated
CloseoutPhotos, approvals, instructions, punch listNot statedNot statedNot stated

Separate four kinds of price

Base price is the contractor’s amount for a defined scope. The definition matters as much as the amount.

Allowance is a stated provision for work or selections that are not fully resolved. Ask how the allowance is reconciled and whether unused amounts are credited. A bare allowance amount does not explain the quantity or quality included.

Unit price is a rate for a specified measurable item. Record the unit, measurement method, and whether labor, material, disposal, overhead, and access are included. “Sheathing: $X” is not an adequate unit description.

Alternate is an explicitly priced variation from the base scope. Keep alternates separate until the owner selects them. A different finish, additional elevation, or optional upgrade should not appear in only one bidder’s unqualified total.

Avoid adding all allowances and alternates automatically. Some alternatives replace base work; adding both would double count the same item.

Use a clarification register

Assign each unresolved item a number and ask for a written response by a common deadline.

IDQuestionResponse neededStatus
C-01Does the proposed flashing scope include existing windows that remain?Specific retained/replaced details and exclusionsOpen
C-02How are concealed repairs measured and approved?Unit definition, evidence, and authorization processOpen
C-03Who obtains required permits and schedules inspections?Named responsible entity and included feesOpen
C-04What changes if the start date moves?Price validity, availability assumptions, schedule consequencesOpen
C-05What is delivered before final payment?Contractual closeout list and acceptance processOpen

“Included as needed” may still be ambiguous. Ask the bidder to describe what is included, what triggers extra work, and how an extra is authorized.

Record risks without pretending to calculate them precisely

A low base price and a large unresolved exclusion can create budget uncertainty. That does not mean the exclusion will become a charge; it means the owner lacks information needed for a decision.

Use plain labels such as resolved, needs investigation, owner decision, or contract clarification. Resist assigning numerical risk scores unless everyone understands the method and its limitations.

For a difficult concealed condition, the next step may be a limited investigation, not another round of guessing. Price that investigation explicitly and make its findings available for the next scope revision.

Verify qualifications against the actual work

Oklahoma’s CIB states that general contractors are not currently required to hold a state general-contractor license, while regulated trades and local requirements remain separate. Avoid using an undefined “Oklahoma licensed” badge as a shortcut. Oklahoma Construction Industries Board.

Ask for the contracting entity’s legal name, relevant work history, required trade registrations or licenses, local requirements, and insurance documentation appropriate to the project. Have the owner’s adviser check the proposed insurance requirements and endorsements. Obtain the actual warranty terms before treating a warranty duration as an advantage.

Reference checks should address comparable occupied-building work. Ask what the contractor did, how changes were handled, and whether the owner received useful closeout records. A product training credential and a successful multifamily installation are different pieces of evidence.

Write the selection memo before signing

A useful selection memo states the accepted scope revision, evaluated proposals, resolved clarifications, selected alternatives, remaining assumptions, and reason for the choice. Attach the documents that support it.

The reason need not be “lowest price.” It might be clearer scope, a workable resident plan, better-documented relevant experience, or an acceptable schedule. Make that reasoning visible to the people who approve the commitment.

Use the selected proposal, clarification responses, drawings, and specifications to prepare a coherent contract. If those documents contradict one another, resolve the conflict before work begins rather than expecting the project team to improvise later.